logo

Certified Associate in Project Management Exam

Home / Project Management & HR / Project Management Professional

Question 1 of 5.

A project manager is working with a Simon team that is continually making decisions. The steering committee is concerned about the project as it is not clear that it will deliver the expected value. After some analysis, the project manager discovers there is a mismatch of competencies in one of the teams. What should the project manage do?

A. Actual the size of the project missing deadlines due to the mismatch.

B. Emphasize to the teams the importance of meeting the agreed deadlines.

C. Provide appropriate training to compensate for the mismatch.

D. Update the project schedule to reflect the delay.

Explanation: The root cause of the problem (delivering no value, missing deadlines) is a competency mismatch. The most proactive and effective solution is to address this root cause directly by providing training to upskill the team. This enables the team to make better decisions and deliver value, rather than just acknowledging the delay (A, D) or pressuring the team (B).

Question 2 of 5.

A client is structured as a main organization for an agile project. The project manager is working on-site with key stakeholders from different parts of the organization. How should the project manager handle the different stakeholders?

A. All stakeholders are important, so the project manager should follow directions provided by management and key stakeholders.

B. Because there are different perspectives, perform a stakeholder analysis and act based on the outcome.

C. The project manager is working on the client's premises, via follow-the direction of all the key stakeholders.

D. This is an agile project, so listen only to the directions of the project managers' supervisor and the functional managers of the organisation.

Explanation: Performing a stakeholder analysis is a key step in stakeholder management. It helps identify interests, influences, and potential conflicts, allowing the project manager to engage effectively. Agile projects emphasize collaboration, but blindly following all directions without analysis can lead to conflicts and misalignment. Option B is the most proactive and structured approach.

Question 3 of 5.

The role of a new finance engineer is the standard-private function of which have surfaced in the last month that are slowing the project down. A new project sponsor has recently started with the company full-time not had time to meet the project needs. The prospect is the point where the launch was significantly updating delivery of the project. How should the project manager start the new project sponsor about these accounts?

A. Since an email to the project sponsor summarising the project status and key concerns, and requests an immediate face-to-face meeting to discuss them.

B. Send an email invitation to the project sponsor to attend all of the project teams weekly meetings, and keep the sponsor set foot time to attend.

C. Continue emailing updated project status reports highlighting the key risks and issues, and wait for the project sponsor to respond a meeting.

D. Complete a risk analysis auditing the driving team process, and email a copy of the risk register, urging the project sponsor to respond.

Explanation: The project sponsor is critical for resolving issues and providing support. Given the urgency, a direct summary of status and concerns followed by a request for a face-to-face meeting is the most effective way to engage the sponsor promptly. Waiting for a response (Option C) or sending invitations to all meetings (Option B) might delay action. Option D is reactive and not as direct.

Question 4 of 5.

Any project stakeholder showed interest in the supporting of a complete right project, but has become less involved at the agent has progressed due to additional responsibilities. After sports time, the key stakeholder requires a flexible description. The team can manage this updated observation for the next sprint. What should the project manager have done to build the situation?

A. Documented the project vision and objectives

B. Analyzed the changes in stakeholder attributes

C. Customized stakeholder communications based on the stakeholders' needs

D. Numbered the key stakeholders in the decision-making process

Explanation: Stakeholder engagement is an ongoing process. The stakeholder's reduced involvement due to additional responsibilities indicates a change in their attributes (e.g., availability, influence). Analyzing these changes early would allow the project manager to adjust engagement strategies and prevent miscommunication or delays.

Question 5 of 5.

The change control board (CCB) reports a change request submitted by a subject matter expert (BNF). The SME relates to except the injection and does not want to continue the project without the change. What should the project manager have done to avoid this situation?

A. Requested that the sponsor approved the change request first.

B. Ensured that the change request was aligned with the project scope.

C. Assessed the change's overall impact to the project before submission.

D. Submitted the change request directly to the CCB.

Explanation: Change requests must be evaluated for their impact on scope, schedule, cost, quality, resources, and risks before submission to the CCB. This assessment ensures that the change is properly reviewed and avoids unnecessary conflicts or delays. Option C is a standard practice in change management.

Related Questions

During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting. The ongoing conflict is preventing tasks and deliverables from being completed. The project manager contemplates changing their leadership style. What should the project manager do?

A project is in the knowledge transfer phase, and a few subject matter experts (SMEs) want to the client side for knowledge transfer. The SMEs captured various process donations without sharing with the project team. How should the project manager ensure knowledge transfer across the team?

A vendor informed the project manager that a critical resource will be on a long leave of absence. The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost. The project is currently an schedule and slightly under budget. What should the project manager do next?

With training a range, the project manager has just worked for the last several monthly minutes have been challenging by the client when they were closely advised. The actual invoice payments received have also been late and were outside of the continuing payment schedule. Allotted amounts have only been partially paid. Work should be posted manager do?

A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why those reviews are held to frequently. How should the project manager respond?

GET IN TOUCH

+012 345 67890

support@examlin.com

Privacy

Terms

FAQS

Help


© Examlin.All Rights Reserved.