logo

Certified Associate in Project Management Exam

Home / Project Management & HR / Project Management Professional

Question 1 of 5.

A project manager is working on a software development project. A team member completes that issue the project tasks are very simple, there is no reason to perform quality control. The project manager understands that removing the quality management plan from the project will also help to start moving, which is important to the customer. How does this project manage?

A. Ask the audience to solve an external quality audit after accepting the project deliverable, and discuss as the budget of the project.

B. Get confirmation from management that the team members has enough experience to build software without quality control.

C. Denote the quality management plan, as quality is as equally important as cost and schedule management.

D. Require serving the project without a quality management plan as a risk, and discuss the budget savings to the management reserve.

Explanation: Quality is a core component of project management and is non-negotiable. The project manager must uphold the quality management plan, as it ensures the deliverables meet requirements and provides confidence. Sacrificing quality for cost or schedule can lead to rework, failures, and ultimately higher costs and delays, undermining customer value.

Question 2 of 5.

A client is structured as a main organization for an agile project. The project manager is working on-site with key stakeholders from different parts of the organization. How should the project manager handle the different stakeholders?

A. All stakeholders are important, so the project manager should follow directions provided by management and key stakeholders.

B. Because there are different perspectives, perform a stakeholder analysis and act based on the outcome.

C. The project manager is working on the client's premises, via follow-the direction of all the key stakeholders.

D. This is an agile project, so listen only to the directions of the project managers' supervisor and the functional managers of the organisation.

Explanation: Performing a stakeholder analysis is a key step in stakeholder management. It helps identify interests, influences, and potential conflicts, allowing the project manager to engage effectively. Agile projects emphasize collaboration, but blindly following all directions without analysis can lead to conflicts and misalignment. Option B is the most proactive and structured approach.

Question 3 of 5.

The role of a new finance engineer is the standard-private function of which have surfaced in the last month that are slowing the project down. A new project sponsor has recently started with the company full-time not had time to meet the project needs. The prospect is the point where the launch was significantly updating delivery of the project. How should the project manager start the new project sponsor about these accounts?

A. Since an email to the project sponsor summarising the project status and key concerns, and requests an immediate face-to-face meeting to discuss them.

B. Send an email invitation to the project sponsor to attend all of the project teams weekly meetings, and keep the sponsor set foot time to attend.

C. Continue emailing updated project status reports highlighting the key risks and issues, and wait for the project sponsor to respond a meeting.

D. Complete a risk analysis auditing the driving team process, and email a copy of the risk register, urging the project sponsor to respond.

Explanation: The project sponsor is critical for resolving issues and providing support. Given the urgency, a direct summary of status and concerns followed by a request for a face-to-face meeting is the most effective way to engage the sponsor promptly. Waiting for a response (Option C) or sending invitations to all meetings (Option B) might delay action. Option D is reactive and not as direct.

Question 4 of 5.

Any project stakeholder showed interest in the supporting of a complete right project, but has become less involved at the agent has progressed due to additional responsibilities. After sports time, the key stakeholder requires a flexible description. The team can manage this updated observation for the next sprint. What should the project manager have done to build the situation?

A. Documented the project vision and objectives

B. Analyzed the changes in stakeholder attributes

C. Customized stakeholder communications based on the stakeholders' needs

D. Numbered the key stakeholders in the decision-making process

Explanation: Stakeholder engagement is an ongoing process. The stakeholder's reduced involvement due to additional responsibilities indicates a change in their attributes (e.g., availability, influence). Analyzing these changes early would allow the project manager to adjust engagement strategies and prevent miscommunication or delays.

Question 5 of 5.

The change control board (CCB) reports a change request submitted by a subject matter expert (BNF). The SME relates to except the injection and does not want to continue the project without the change. What should the project manager have done to avoid this situation?

A. Requested that the sponsor approved the change request first.

B. Ensured that the change request was aligned with the project scope.

C. Assessed the change's overall impact to the project before submission.

D. Submitted the change request directly to the CCB.

Explanation: Change requests must be evaluated for their impact on scope, schedule, cost, quality, resources, and risks before submission to the CCB. This assessment ensures that the change is properly reviewed and avoids unnecessary conflicts or delays. Option C is a standard practice in change management.

Related Questions

A key project stakeholder who was a big supporter and merchant for the project team is leaving the organization. The project team is experiencing low morale and poor teamwork. What should the project manager do to improve morale?

After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run. What has actions should the project manager take? (Choose 3)

A team has been working on a project for tenant months, but the complete date is finished because the scope is changing frequently as new knowledge is gained. Some deliverables have already been completed, but when new stakeholders join the team, they complete that project following up and meeting business goals. How should the project manager present this situation from happening in the future?

A company that is heavily focused on delivering projects using predictive approaches as brands a new project manager who uses hybrid approaches. The scope of the project contains a number of unclear requirements. How should the project manager plan the delivery of the project?

To address the costs of a new project that is unable to go project that was implemented last year, the project manager meets with a group of experts from the previous project. The group uses a three-piece estimating technique. The project manager intends the estimated budgets to be applied forward for approval. The project sponsor, who is one in the company, is concerned because the budget exceeded their expectations. What should the project manager do?

GET IN TOUCH

+012 345 67890

support@examlin.com

Privacy

Terms

FAQS

Help


© Examlin.All Rights Reserved.